Proposed Power Plant Project Timeline

AUC Permit Update Submission

Q2 2022

Phase 1 Construction and turbine erection

Q2 2023 - Q3 2024

Anticipated AUC Approval

Q3 2022

Phase 1 Commercial Operations

Q3 2024

Municipal Development Permit Submission and Approval

Q3 2022 / Q1 2024

Phase 2 Construction and Turbine Erection

Q2 2024-Q1 2025

Anticipated Start of Construction

Q3 2022

Phase 2 Commercial Operations

Q3 2025

 

Proposed Interconnection Project Timeline

AUC Application Submission Q2 2022
Anticipated AUC Approval Q4 2022
Municipal Development Permit Submission and Approval Q4 2022
Anticipated Start of Construction Q4 2022 / Q1 2023
Commercial Operations Q2 2023