Proposed Power Plant Project Timeline
AUC Permit Update Submission |
Q2 2022 |
Phase 1 Construction and turbine erection |
Q2 2023 - Q3 2024 |
Anticipated AUC Approval |
Q3 2022 |
Phase 1 Commercial Operations |
Q3 2024 |
Municipal Development Permit Submission and Approval |
Q3 2022 / Q1 2024 |
Phase 2 Construction and Turbine Erection |
Q2 2024-Q1 2025 |
Anticipated Start of Construction |
Q3 2022 |
Phase 2 Commercial Operations |
Q3 2025 |
Proposed Interconnection Project Timeline
AUC Application Submission | Q2 2022 |
Anticipated AUC Approval | Q4 2022 |
Municipal Development Permit Submission and Approval | Q4 2022 |
Anticipated Start of Construction | Q4 2022 / Q1 2023 |
Commercial Operations | Q2 2023 |